Handover inspection checklist

Walk the unit in the same order every time and you will miss less. This is the checklist we see engineers use, area by area, and what to record when something fails.

Before you start

Five minutes at the door saves an hour at the desk.

  • note the date, time on site and weather;
  • agree the room names with the client, so locations match the drawings;
  • switch on power and water, and run the AC for the whole visit;
  • start at the top floor and work down, room by room, clockwise.

Walls, ceilings and floors

  • cracks in plaster, especially above lintels and at corners;
  • paint: patchy coats, drips, colour mismatch at touch-ups;
  • tiles: hollow sound, lippage between tiles, cracked or chipped edges, missing grout;
  • skirting: gaps at the wall, loose sections;
  • ceilings: level of bulkheads, gaps around AC grilles and lights.

Doors and windows

  • every door closes and latches without force, and locks with its key;
  • frames are plumb, with even gaps and no damage to the finish;
  • windows open, close and lock; seals are continuous;
  • glass has no scratches; sliding doors run without catching.

Bathrooms, kitchen and wet areas

  • silicone is continuous at the shower tray, basin and worktop;
  • water pressure and hot water at every outlet;
  • drains run fast, with no smell and no standing water on the floor;
  • no leaks under basins and sinks after a few minutes of running.

MEP

  • distribution boards are labelled, with no unterminated cables;
  • every socket and switch works and sits flush;
  • the AC cools in every room and the FCU drains cleanly;
  • smoke detectors are fitted where the drawings show them.

Recording what fails

A checklist tells you where to look. The report is what fails: one finding per defect, with its location, a photo, the observation in your words, the measurement you took, a severity and an action. Items that pass do not need a line each; say in the summary which areas were inspected.

See the real thing

This sample was printed by Arkan Siteseal from a sample visit with three real findings. It has every section above.

The sample report, section by section

  1. Masthead: firm, report title, number and revision
  2. Title block: site, client, date, time on site, engineer, weather
  3. Executive summary: counts by severity, then the overview
  4. Recommended actions, numbered by severity with F-references
  5. Findings: photo, location, observation, severity, action
  6. Signatures, with name, registration number and time
  7. Footer on every sheet: report number and sheet x of y
Sheet 1 of the English sample: masthead, title block, executive summary, recommended actions and the first finding.